Temporary Services
Temporary Services – General
Section E-1
Provisions for anticipated Temporary Services should be incorporated in the General Requirements of the specifications, but not in each product specification section. The responsibilities of each of the mechanical and electrical Contractors (or subcontractors) should be specifically defined where there are separate mechanical and electrical contractors, but not where work is under a single Prime Contractor.
When appropriate, the following Temporary Services should be addressed:
- Heat – as recommended in Section E-2
- Light & Power – as recommended in Section E-3
- Water supply – as recommended in Section E-4
- Barricades, Fending, Sidewalk protection
- Stairs, Netting and Planking for multi-story buildings
- Offices for field Superintendent/Inspector/etc.
- Sheds for Carpenters/Brick Layers/Laborers/Storage/etc.
- Toilets/Sewage
- Enclosures
- Telephone
- Roads
- Hoisting/Crane
- Scaffolding
- Winter protection (when applicable)
- Travel/Room and Board
- Fire Suppression equipment
- Fire Watches
- Signage
- Daily clean-up/Final clean-up
- Traffic Control
- Pedestrian protection/Walkways/Egress
This list should be considered an overview. There may be other temporary Services that should be addressed for a particular project, and should be incorporated into that project.
Glossary Terms for the Best Practices Guide
History of Recommendation:
Reviewed March, 2010
Revised April, 1988
Revised April, 1987
Revised November, 1977
Revised November, 1971
Temporary Heat and Its Related Power (Including Fuel, Labor, Filters, Warranties, etc.)
Section E-2
Prior to enclosure of the building, buildings or portions thereof, and when weather conditions indicate the necessity for temporary heat, the Contractor shall provide, maintain, operate and pay costs, including fuel for the sufficient number of approved portable heaters so that progress of the work is not impeded.
After the building, buildings or portions thereof are enclosed, and temporary heat is required for construction, temporary heat shall be provided by the HVAC Contractor. Fuel is to be supplied by the Contractor for new/unoccupied buildings; fuel is to be supplied by the Owner for occupied buildings undergoing additions or renovations.
1. In lieu of the permanent heating system, the Heating Contractor may provide, install, and maintain a temporary heating system of a type approved by the Architect, provided it is properly vented.
2. Labor
Labor for the operation and maintenance of temporary heat systems shall be provide by the Mechanical Contractor, except that labor for the operation and/or maintenance of electrical control and power systems shall be borne by the Electrical Contractor.
3. Filters and filter Labor
If permanent system is used for temporary heat, appropriate filters are to be used until Substantial Completion and shall be furnished by the Mechanical Contractor. These shall be replaced (including labor for replacement) by the Mechanical Contractor with new filters of the specified type.
4. Extension of Warranties
The warranty period of individual pieces of equipment used during, and for, the temporary heat period, shall be extended so that the starting date for the warranties shall be the date of Substantial Completion.
5. Cleaning
The General Contractor shall remove from exposed surfaces deposits which are a result of the use of any temporary heating equipment, including from the use of the permanent heating system for temporary heat purposes. He shall not do any finish work until such surfaces are properly cleaned. Prior to final acceptance, all permanent heating equipment used to supply temporary heat shall be completely cleaned and reconditioned by the Heating Contractor.
Any Contractor who fails to carry out his responsibility in supplying temporary heat as set forth in this Contract, shall be held responsible for such failure. The Owner shall have the right to take such action as he deems proper for the protection and conduct of the work, and shall deduct the cost involved from the amount due the Contractor at fault.
Glossary Terms for the Best Practices Guide
History of Recommendation:
Reviewed March, 2010
Revised April, 1987
Temporary Light and Power
Section E-3
The Electrical Contractor shall furnish all labor and material necessary for a complete temporary lighting and power system throughout the project except as hereinafter modified. The Owner shall provide necessary tap-ins. The Electrical Contractor shall be responsible for the cost of temporary power in new/unoccupied buildings; the Owner shall be responsible for the cost of temporary power in occupied buildings undergoing addition or renovation.
The Electrical Contractor shall provide these temporary systems within fifteen (15) days after written request by any Contractor requiring the system, with copies going to interested parties.
The temporary lighting and power systems shall include the following:
- Service to the building.
- Metering, main fused disconnect switch, current limiting fuses, grounding panel boards and feeder circuits.
- Distribution throughout the building as required by local, state, and national codes.
- Lighting system to satisfy (minimum) local, state, and national codes.
- Power system, including branch wiring (separate from lighting) with ground wire and grounding type 120 volt 20 ampere ground type duplex convenience outlets, located as follows:
a. for corridors – outlets on 50 foot centers;
b. for other spaces – outlets shall be located so that the addition of a 50 foot extension cord will extend power to any area within the space.
c. Maximum of four outlets per 20 ampere circuit. - Power to construction trailers and offices for lighting and air conditioning.
- Labor for operation and maintenance of temporary heat systems shall be provided by the Mechanical Contractor except that labor for the operation and/or maintenance of electrical control and power systems shall be borne by the Electrical Contractor.
- Testing and reporting per the latest OSHA Standards.
The following are suggested capacities for temporary light and power:
Gross Square Feet Capacity
Up to 50,000 100KVA
50,000 to 100,000 150 KVA
100,000 to 250,000 300 KVA
250,000 to 500,000 500 KVA
500,000 to 800,000 750 KVA
Each Prime Contractor shall:
1. Bear the cost for providing power and service to their equipment which cannot be served from the systems provided herein.
2. Provide their own extension cords.
3. Bear the cost for any additional lighting they may require for night work and reimburse the Electrical Contractor for any standby personnel per the current labor Contract.
4. Maintain their equipment.
5. Repair and refinish their own work which may have been damaged by removal of temporary system facilities.
When permanent service becomes available, The Electrical Contractor may connect the temporary system to the permanent service with the owner’s approval.
The Electrical Contractor shall maintain the temporary system in working order throughout the period of construction. He shall replace burned-out and missing lamps.
The location of main temporary service and distribution equipment shall be coordinated with affected Prime Contractors on the project.
The temporary systems installed shall be in accordance with requirements of the Local Building codes and local regulations.
The Electrical Contractor shall make the necessary adjustments to the temporary systems to eliminate interruptions which occur as construction progresses.
At the completion of the construction and test period, the Electrical Contractor shall remove all temporary system facilities from the site and replace lamps, ballasts, etc., which are connected to the permanent system, as required.
Any contractor who fails to carry out his responsibility in supplying temporary light and power as set forth in this contract, shall be held responsible for such failure. The Owner shall have the right to take such action as he deems proper for the protection and conduct of the work, and shall deduct the cost involved from the amount due the Contractor at fault.
Glossary Terms for the Best Practices Guide
History of Recommendation:
Reviewed March, 2010
Revised April, 1987
Temporary Water Supply
Section E-4
The Plumbing Contractor shall construct the permanent water supply line to an appropriate location as required and shall maintain this line, protecting it from damage.
The determination of available water service is the responsibility of the Owner. The Owner shall advise the Contractors of the water supply availability in advance of the bids.
The Plumbing Contractor shall provide, protect, and maintain an adequate water supply for the use of Contractors on the project during the period of construction, either by means of the permanent water supply line or by the installation of a temporary water supply line. This water supply line shall be made available within fifteen (15) days after written request has been made to the Plumbing Contractor by any Contractor requiring this service, with copies to interested parties.
If the water is currently metered, the Owner will bear the charges. If the water is not currently metered, the General Contractor will bear the charges. Service connection fees and usage fees should be the responsibility of the Owner.
When temporary water lines are no longer required, they shall be removed by the Contractor responsible for their installation and any part, or parts, of the grounds or buildings disturbed or damaged shall be restored to their original condition.
Any Contractor who fails to carry out his responsibility in supplying temporary water as set forth in this contract, shall be held responsible for such failure. The Owner shall have the right to take such as action as he deems proper for the protection and conduct of the work, and shall deduct the cost involved from the amount due the Contractor at fault.
Glossary Terms for the Best Practices Guide
History of Recommendation:
Reviewed March, 2010
Revised April, 1987