AIA MBA Joint Committee logo   spacer
About UsBest Practices GuideGlossaryHot TopicsContact UsHome
 
 
top
  Best Practices Guide

Drawings & Specifications

Bidding

Contracts

Temporary Services

Bonds, Insurance, & Liability

Safety Responsibilities

Release of Liens

Procurements & Supplements

Miscellaneous

Project Collaboration - Best Practices
 
bottom


  New construction

Contracts


Section D-1
Changes in the Work

Whenever a change in the work is required, the Joint Committee recommends that an adjustment in the contract sum be made on a lump sum basis. The amount for such changes is to be submitted by the contractor, and agreed to by the Architect and Owner, with a formal change order issued, before the work is commenced.

When a lump sum agreement is not practical, the changes may be performed on a cost-plus basis, with a reasonable allowance for overhead and profit, or an agreed-upon unit price basis in accordance with the requirement of the General Conditions of the Contract.

A change in the work may also require a change in the contract time. Time extension should be agreed upon at the same time as the change in the contract sum. All parties involved in the project, including all subcontractors, should be allowed to evaluate changes and be notified of all agreed-upon changes and/or time extensions.

TAGS: Change Order and Lump Sum.

Glossary Terms for the Best Practices Guide

History of Recommendation:
Revised October, 2009
Revised January, 1990
Reviewed April, 1987
Revised December, 1981
Revised September, 1981
Reviewed April, 1976
Revised November, 1971
Revised January, 1967
Approved September, 1958


Back to Contracts
 
     

About Us | Best Practices Guides | Glossary | Hot Topics | Contact | Home
© 2023 AIA MBA Joint Committee
spacer